Context: A French energy group wanted the support of an experienced contract manager to manage performance of a design and build contract…

Pierre MarchèsPartner · fondateur
Case study: managing an EPC contract in the renewables sector

Context:

A French energy group wanted the support of an experienced contract manager to manage performance of a design and build contract for a renewable energy production plant.

Requirement:

The client already had a few contract managers and some early good practice in contract management, and was looking for an experienced profile, operational quickly, able to work in tandem with the project manager. Another objective was to use this contract as an opportunity to introduce new tools and best practices across the group and its various subsidiaries.

Prime Conseil’s involvement

An experienced contract manager with more than fifteen years’ experience of major projects, FIDIC contracts and EPC contracts in the nuclear and renewables sectors was mobilised. Over the two years of construction on site, he was able to:

  • Begin with an analysis of the various contracts (client, end client, suppliers, partners, and so on) and report back to the operational teams through a “contract awareness” pack and presentation designed to make every project stakeholder aware of the content of the contract and of the rights and obligations it creates, as well as of its risks and opportunities
  • Adapt the existing tools for risk and opportunity analysis, correspondence tracking, reporting and claim management to make them more interoperable, easier for operational staff to understand and, above all, to save time for every stakeholder
  • Provide day-to-day monitoring of the project and of how risks and opportunities were evolving, while also anticipating risky contractual situations and dealing with the project’s uncertainties and unknowns
  • Draft contract amendments, claim letters and various requests (EoT, change), working with the project’s and the site’s legal, technical and operational contacts
  • Handle contract management across the whole subcontracting chain (supplier contract management), and in particular monitoring of deliverable quality and claims on time and quality
  • Work with various internal contacts on strategies for negotiating contract amendments and claims in the light of what the contract allowed
  • Carry out a continuous lessons-learned exercise to contribute to the ongoing improvement of contract management at the client

Outcome:

The project, initially due to run for 18 months, was delivered in 24 months, and the negotiation of contract amendments (both on time and on cost), together with the optimisation of the supplier contracts, made it possible to complete the project within the client’s target operating margin, a genuine success for a project of this scale involving both technology risk and weather uncertainty.

Expertise
L'auteur
Pierre Marchès

Fondateur de Prime Conseil, Pierre pratique le contract management depuis quinze ans, au sein de grands groupes comme d'ETI, ainsi qu'auprès de collectivités et de ministères français et étrangers. Il est spécialisé dans l'énergie, l'infrastructure et la défense.

Suivre Pierre sur LinkedInLire les 90 articles de Pierre
Le blog

Nos derniers articles.

Voir tous les articles
Staffing03/08/2026
Recruiting contract managers: why the talent shortage does not explain everything
Recruiting contract managers is regularly presented today as a market facing a shortage. The diagnosis is often the same: the pool of professionals is said to have become…
Lire l'article →
Claims16/07/2026
Preparing a letter: everything is decided before the drafting stage
In a previous article on claims under FIDIC contracts, we saw that form determines the very existence of a claim: a perfectly well-founded right but…
Lire l'article →
FIDIC09/07/2026
Claims under FIDIC contracts: when form matters as much as substance
On most projects, a received idea holds that a claim is won on substance. The idea is appealing: the claim would be a matter for technicians and experts…
Lire l'article →

Let's get to know each other.

By email
contact@primeconseil.com
For the shy ones.
In person
1192, Bd Jean Baptiste Abel, 83000 Toulon38, Rue Jean Bouchet, 86000 Poitiers3 Bis, Rue Taylor, 75010 Paris
For the coffee lovers.
By phone
(+33) 04 12 33 31 01
For the straight talkers.
Emailcontact@primeconseil.comFor the shy ones.Phone(+33) 04 12 33 31 01For the straight talkers.
In person1192, Bd Jean Baptiste Abel, 83000 Toulon38, Rue Jean Bouchet, 86000 Poitiers3 Bis, Rue Taylor, 75010 Paris